↳About the work
Industrial project consists of Production area (1088m2), Incinerator (160m2), Storage (739m2), Transportation Sterilizing (108m2), Liquid storage (140m2), LPG facility (108m2), administration/laboratory (245m2), guardhouse building. The project will serve BOOM construction – Waste treatment department recycling activities for hazard wastes (i.e. oil sludges, healthcare, etc.) and supplementary warehouse pre-treated materials, treated materials, spare parts and consumables. The above buildings will be located in a MIC plot of 7500m2 and it is the 1st phase of the project. The 2nd phase includes about 160m2 of a 2nd incinerator installation extension.